Safe Work Method Statement for Concrete Pile Removal and Demolition

Concrete Pile Removal SWMS

Australian WHS Compliant

No credit card required • Instant access • 100% compliant in every Australian state

5 sec
Creation Time
100%
Compliant
2,000+
Companies
$3.6K
Fines Avoided

Avoid WHS penalties up to $3.6M—issue compliant SWMS to every crew before work starts.

Concrete pile removal is a specialised demolition and civil engineering activity involving the extraction, breaking, or cutting of existing foundation piles to facilitate site redevelopment, structural modifications, or remediation works. This work encompasses the removal of various pile types including driven precast concrete piles, bored cast-in-place piles, driven steel casings filled with concrete, and micro-piles used for underpinning or ground improvement. Removal methods range from mechanical breaking using hydraulic breakers and crushers, cutting using diamond wire saws or concrete saws, chemical expansion breaking using non-explosive demolition agents, to full extraction by gripping and pulling piles from the ground using specialised pile extraction equipment. Pile removal operations present significant hazards including dust inhalation from concrete breaking and crushing generating high levels of respirable crystalline silica, flying debris from concrete fragmentation striking workers or damaging property, ground instability from undermined foundation piles affecting adjacent structures, noise and vibration exposure from repeated impact breaking, and confined space hazards when excavating around pile bases. This Safe Work Method Statement provides comprehensive guidance for safely executing concrete pile removal activities in accordance with Australian WHS legislation, relevant Standards including AS 2187 for demolition work, and industry best practices for structural demolition and civil remediation projects.

Unlimited drafts • Built-in WHS compliance • Works across every Australian state

Overview

What this SWMS covers

Concrete pile removal represents a complex demolition activity undertaken during site redevelopment projects, structural modifications requiring foundation changes, remediation of defective piling installations, or demolition of existing structures where pile foundations must be removed rather than abandoned in-ground. The work differs fundamentally from standard structural demolition due to the buried nature of piles, substantial reinforcement within pile elements, high-strength concrete specifications typically used in foundation construction, and potential for ground instability when load-bearing piles are removed from soil that has consolidated around them over years or decades. Pile removal scope varies dramatically from small-scale extraction of several residential timber or small-diameter concrete piles for minor building works, to major infrastructure projects requiring removal of hundreds of large-diameter bored piles (600-1200mm diameter) from bridge foundations or high-rise developments being demolished and redeveloped. Removal methodology selection depends on multiple factors including pile type and construction method (driven precast versus cast-in-place affects ease of removal dramatically), pile dimensions (diameter, length, reinforcement density), site constraints (access limitations, proximity to occupied structures, environmental restrictions), and intended future use of the site (full removal required if new foundations will be installed, truncation at depth acceptable if site will be developed differently). Common removal approaches include: mechanical breaking using hydraulic rock breakers mounted on excavators progressively fracturing concrete from pile head downward, typically effective for smaller diameter piles (up to 450mm) but becoming inefficient for heavily reinforced large-diameter elements; hydraulic crushing using purpose-built pile-crunching attachments that grip and fracture concrete while leaving reinforcement intact for cutting and removal; diamond wire cutting creating horizontal cuts allowing pile removal in manageable segments, particularly effective for large-diameter piles where breaking would be excessively slow; chemical expansion breaking using non-explosive expansive grout injected into drilled holes causing controlled fragmentation over 24-48 hours, valuable in vibration-sensitive environments; and full extraction using pile gripping equipment that clamps pile head and progressively pulls entire pile from ground, feasible only for driven piles in suitable soil conditions where extraction forces do not exceed equipment capability. Pile removal typically progresses through systematic stages beginning with desktop review of as-built documentation identifying pile locations, dimensions, specifications, and construction records providing insight into pile concrete strength and reinforcement details. Site investigation may involve test excavation to physically expose and inspect actual pile conditions, particularly important where original documentation is incomplete or suspect. Structural engineering assessment evaluates load transfer from any remaining structures, determines safe removal sequence preventing progressive collapse or excessive loading on adjacent piles, and specifies temporary works requirements such as propping or underpinning. Following engineering approval, excavation commences around pile heads, typically requiring 1-2 metres depth excavation creating working platform for demolition equipment while exposing sufficient pile length for equipment attachment. Pile breaking or cutting proceeds using selected methodology, with progressive removal of broken segments preventing excessive debris accumulation in excavation. Pile voids created by removal require immediate backfilling using controlled fill material compacted in layers to prevent future ground settlement that could damage surface structures or utilities. Environmental management throughout pile removal focuses on dust suppression given extremely high dust generation from concrete breaking, noise and vibration monitoring protecting adjacent properties, and groundwater management where pile removal intercepts water-bearing strata. The work demands specialised skills and equipment including demolition operators experienced in controlled concrete breaking, riggers competent to safely lift irregular heavy concrete segments, geotechnical awareness to recognise unstable ground conditions and stop work before collapse occurs, and supervisory oversight ensuring structural engineering specifications are followed and adjacent structures continually monitored for any movement indicating excessive impact from removal operations. Site safety is paramount given the combination of demolition hazards, excavation risks, heavy lifting operations, and potential for catastrophic ground failure if removal undermines adjacent foundations beyond acceptable limits specified in structural engineering assessments.

Fully editable, audit-ready, and aligned to Australian WHS standards.

Why this SWMS matters

Concrete pile removal constitutes high-risk construction work under multiple categories defined in Schedule 3 of the Work Health and Safety Regulations 2011, specifically including demolition of load-bearing structures, work involving structural alterations requiring temporary support structures, and excavation work exceeding 1.5 metres depth typically required to access pile heads. Persons conducting a business or undertaking (PCBUs) are legally obligated to prepare, consult on, and implement SWMS before commencing such high-risk activities, with substantial penalties applying for non-compliance including immediate prohibition notices stopping work, improvement notices requiring corrective action within specified timeframes, and prosecution following serious incidents. Beyond regulatory obligation, the severe injury potential from pile removal hazards makes comprehensive SWMS development a critical safety management function protecting workers from life-threatening exposures. The primary health hazard in concrete pile removal is respirable crystalline silica dust exposure generated from mechanical breaking and crushing of concrete pile elements. Pile concrete typically contains 70-80% crystalline silica in the form of sand aggregate, with breaking operations creating substantial quantities of fine respirable dust particles less than 10 microns diameter that penetrate deep into lung tissue when inhaled. Unlike larger dust particles cleared by respiratory system defences, respirable silica particles lodge in lung alveoli causing chronic inflammation, fibrosis, and ultimately silicosis—an irreversible and potentially fatal lung disease with no cure once developed. Safe Work Australia estimates that over 600,000 Australian workers are potentially exposed to silica dust, with construction and demolition workers representing a substantial proportion. Recent regulatory changes implementing a strengthened exposure standard of 0.05 mg/m³ time-weighted average (reduced from previous 0.1 mg/m³) reflect growing evidence that even low-level chronic silica exposure causes serious health effects. Pile removal operations conducted without comprehensive dust suppression can generate atmospheric silica concentrations hundreds of times above permissible exposure limits within minutes, creating acute exposure situations requiring immediate control. Flying debris from concrete fragmentation during breaking operations presents severe struck-by hazards, with concrete fragments propelled outward at high velocity (up to 10-15 metres distance) as hydraulic breakers shatter material under tremendous force. Workers operating breaking equipment, personnel observing operations, and people in adjacent areas face risks of serious head injuries, eye injuries including permanent blindness, lacerations, and blunt force trauma. The unpredictable nature of concrete fracture means debris projection direction cannot be reliably anticipated, making exclusion zones and physical barriers essential controls. Property damage from flying debris striking vehicles, buildings, or glazing compounds injury risks and creates civil liability exposures. Ground instability hazards arise when removing load-bearing piles that have supported structures for extended periods, during which time surrounding soil has consolidated and potentially become dependent on pile presence for stability. Removing piles can trigger ground settlement affecting adjacent structures, utilities, or roadways, with settlement potentially occurring suddenly rather than gradually. Excavation around pile heads to access pile for breaking equipment creates additional instability risks, particularly in cohesionless soils (sands, gravels) where excavation walls can collapse suddenly, or in cohesive soils (clays) where apparent stability may be undermined by groundwater seepage or vibration from breaking operations. Excavation collapse can bury workers within seconds, with rescue complicated by unstable soil preventing safe access to trapped personnel. Vibration from pile breaking operations, particularly repeated impact using hydraulic breakers, generates ground-borne vibration that can damage adjacent structures through fatigue cracking in masonry, displacement of structural elements, or exacerbation of pre-existing structural defects. Heritage buildings, unreinforced masonry structures, and buildings with existing damage are particularly vulnerable. Vibration can also disturb contaminated soils releasing hazardous materials, or trigger instability in marginally stable slopes or excavations. Whole-body vibration exposure affects equipment operators, with chronic exposure potentially causing lower back pain, digestive disorders, and cardiovascular effects. Hand-arm vibration from breaker operation can cause vibration white finger syndrome characterised by numbness, tingling, and reduced manual dexterity potentially becoming permanent with continued exposure. From a business perspective, effective SWMS demonstrate professional capability to clients and principal contractors, increasingly becoming prerequisite for tender submission on projects involving demolition or remediation work. Insurance providers require evidence of comprehensive safety management systems including SWMS before providing coverage for high-risk demolition activities, with premiums reflecting documented safety performance. Following incidents, inadequate SWMS or failure to implement documented controls becomes central focus of WorkSafe investigations, potentially resulting in prosecution of organisations and individual officers. Beyond compliance and liability management, well-developed SWMS improve operational efficiency by establishing clear procedures reducing time spent on site briefings, providing consistent approaches across multiple projects, and facilitating better communication with structural engineers, adjacent property owners, and regulatory authorities regarding safety measures being implemented.

Reinforce licensing, insurance, and regulator expectations for Concrete Pile Removal Safe Work Method Statement crews before they mobilise.

Hazard identification

Surface the critical risks tied to this work scope and communicate them to every worker.

Risk register

Dust Inhalation from Concrete Breaking and Crushing (Silica Exposure)

High

Mechanical breaking and crushing of concrete piles generates extremely high levels of respirable crystalline silica dust, with dust particles less than 10 microns diameter that penetrate deep into lungs when inhaled. Pile concrete typically contains 70-80% silica in aggregate form, with breaking operations fracturing this material into fine airborne particles. Hydraulic breakers produce intense dust clouds obscuring visibility and creating acute exposure situations where atmospheric silica concentrations can exceed permissible limits by factors of 100-1000 times within confined excavations or inadequately ventilated work areas. Unlike larger dust particles cleared by respiratory defences, respirable silica lodges permanently in lung tissue causing chronic inflammation and progressive fibrosis. The confined nature of pile excavations concentrates dust around breaking operations, with workers unable to escape exposure while equipment operates.

Flying Debris from Concrete Demolition Equipment

High

Hydraulic breakers and crushing attachments fracture concrete under tremendous force (typically 1000-3000 joules impact energy for medium breakers, up to 8000+ joules for large units), propelling concrete fragments outward at high velocity. Debris can travel 10-15 metres or more from breaking point, with fragment size ranging from fine particles to substantial chunks weighing several kilograms. Concrete fracture patterns are unpredictable, making debris trajectory impossible to reliably anticipate. Reinforcement steel within piles adds additional hazard as concrete breaks away exposing sharp steel rod ends, and steel reinforcement under tension from breaking forces can suddenly release creating whipping hazards. Workers operating demolition equipment, personnel observing operations, supervisors conducting inspections, and people in adjacent areas all face debris strike risks.

Ground Instability from Undermined Foundation Piles

High

Removing load-bearing piles that have supported structures for years or decades can trigger ground settlement as soil previously stabilised by pile presence undergoes consolidation or shear failure. Pile removal creates voids that may not be immediately apparent if voids extend below excavation depth, with void collapse potentially occurring suddenly rather than gradually. Adjacent structures, utilities, roadways, or landscaping can experience differential settlement causing structural cracking, utility fractures, pavement damage, or complete structural failure in extreme cases. Excavation around pile heads to access piles for breaking equipment creates open excavations typically 1.5-3 metres deep that may collapse if soil conditions unstable, particularly in cohesionless soils (sands, gravels) or when groundwater seepage undermines excavation walls.

Confined Space Hazards in Pile Excavation Cavities

High

Deep excavations around pile bases can create confined space conditions where atmospheric hazards develop including oxygen deficiency from bacterial decomposition of organic material in soil, toxic gas accumulation from sewer gases or buried contaminants, or asphyxiant gas layering (carbon dioxide is heavier than air and accumulates in excavation bottoms). Pile excavations typically have limited egress with workers accessing via ladders, creating difficulty for emergency evacuation or rescue operations. Poor ventilation in deep excavations allows dust to accumulate at hazardous concentrations. Limited working space restricts worker movement and complicates rescue operations if workers injured or overcome by atmospheric hazards.

Noise and Vibration Exposure from Repeated Impact Pile Breaking

Medium

Hydraulic breakers generate intense noise levels typically exceeding 110-120 dB(A) at operator position, well above the 85 dB(A) threshold requiring hearing protection and approaching pain threshold levels. Repeated impact creates ground-borne vibration transmitted through equipment chassis causing whole-body vibration exposure to operators and hand-arm vibration from breaker handles. Extended pile breaking operations over multiple shifts create cumulative noise and vibration exposures. Excavation walls can reflect and amplify noise within confined work areas. Adjacent properties experience environmental noise and vibration impacts potentially causing structural damage, particularly to heritage buildings or structures with pre-existing defects.

Control measures

Deploy layered controls aligned to the hierarchy of hazard management.

Implementation guide

Water Suppression Dust Control Systems

Engineering Control

Implement comprehensive water suppression systems eliminating airborne silica dust at source before particles become respirable and inhalable.

Implementation

1. Deploy continuous water spray systems positioned around breaking equipment, creating water curtain capturing dust at generation point before becoming airborne 2. Utilise misting nozzles producing fine water droplets optimised for dust particle capture (50-100 micron droplet size most effective) 3. Position water supply with adequate pressure (minimum 400 kPa) and flow rate sustaining continuous suppression throughout breaking operations 4. Implement automatic water activation integrated with breaker operation, ensuring water flows whenever breaking occurs and preventing dry breaking 5. Supplement active suppression with water application to pile surfaces before breaking, pre-wetting concrete reducing dust generation potential 6. Contain breaking operations within excavation where practicable, as excavation walls help confine dust and increase water suppression effectiveness 7. Monitor dust generation visually, immediately stopping operations if visible dust clouds develop indicating suppression system inadequacy 8. Maintain water suppression equipment ensuring nozzles clear, supply lines leak-free, and pump systems functioning reliably throughout operations

Physical Debris Containment Barriers and Exclusion Zones

Engineering Control

Create physical barriers containing debris within controlled zone and establish exclusion zones preventing personnel from entering debris projection areas.

Implementation

1. Erect debris containment screening using heavy-duty mesh or solid barriers around immediate breaking operations, positioned to capture or deflect flying fragments 2. Establish exclusion zone minimum 15 metres radius from active breaking operations, marked with barriers and signage prohibiting unauthorised entry 3. Position demolition equipment and breaking points to direct debris toward uninhabited areas away from structures, vehicles, and personnel assembly points 4. Install overhead protection using scaffolding with debris netting or solid decking where breaking occurs beneath structures or in locations where debris could fall onto occupied areas 5. Verify all non-essential personnel withdrawn from exclusion zone before commencing breaking operations, with dedicated observer ensuring zone remains clear 6. Implement clearance procedures requiring equipment operator to verify zone clear before each breaking sequence, using two-way radio communication with ground observer 7. Restrict breaking operations to designated times when adjacent properties unoccupied where debris risk cannot be completely eliminated through physical barriers 8. Provide equipment operator with protected cabin (rather than exposed operator station) where equipment configuration permits, offering inherent debris protection

Geotechnical Assessment and Ground Monitoring

Elimination / Engineering Control

Engage qualified geotechnical engineers to assess ground stability risks, specify safe removal procedures, and implement monitoring detecting ground movement before catastrophic failure occurs.

Implementation

1. Commission geotechnical investigation including soil borings identifying subsurface conditions, groundwater levels, and soil bearing capacity before pile removal commencement 2. Obtain geotechnical report specifying safe excavation depths around piles, required shoring systems, and pile removal sequence preventing excessive ground disturbance 3. Install ground movement monitoring including optical survey targets on adjacent structures, crack width gauges on existing structural cracks, and inclinometers in deep excavations 4. Establish trigger levels for ground movement (typically 5mm immediate action level, 10mm stop-work level) with contingency procedures if movement exceeds limits 5. Conduct daily monitoring surveys before work commencement, during active operations, and after work completion, documenting all readings and comparing to baseline conditions 6. Install excavation shoring immediately upon reaching specified excavation depths, never excavating ahead of shoring installation in accordance with geotechnical specifications 7. Backfill pile voids immediately upon segment removal using controlled fill material compacted in 300mm lifts, preventing void migration or delayed collapse 8. Engage geotechnical engineer for site attendance during critical pile removal operations, providing real-time assessment if unexpected ground conditions encountered

Atmospheric Testing and Confined Space Procedures

Engineering Control / Administrative Control

Implement comprehensive confined space management for deep pile excavations preventing atmospheric hazard exposures.

Implementation

1. Classify all excavations exceeding 1.5 metres depth as potential confined spaces requiring atmospheric testing before entry and continuous monitoring during occupation 2. Conduct atmospheric testing using calibrated multi-gas monitors measuring oxygen percentage (must be 19.5-23.5%), combustible gas levels (must be below 10% LEL), carbon monoxide (must be below 30 ppm), and hydrogen sulfide (must be below 10 ppm) 3. Implement continuous forced ventilation using portable blowers delivering minimum 6 air changes per hour when workers occupied in deep excavations 4. Provide respiratory protection (SCBA or supplied-air respirators) as backup protection if atmospheric hazards detected despite ventilation controls 5. Establish confined space entry permits documenting atmospheric test results, authorised entrants, standby persons, rescue procedures, and communication systems 6. Train all workers entering deep excavations in confined space hazard recognition, emergency egress procedures, and prohibition on entering if atmospheric hazards detected 7. Position standby person at excavation top maintaining continuous communication with workers below and equipped to summon emergency rescue services 8. Provide emergency retrieval equipment (tripod with winch, harnesses, non-entry retrieval capability) at all excavations classified as confined spaces

Vibration Monitoring and Work Hour Restrictions

Administrative Control

Monitor ground vibration protecting adjacent structures and implement work scheduling reducing community impact.

Implementation

1. Install vibration monitoring equipment (seismographs) on adjacent structures recording peak particle velocity and vibration frequency during pile breaking operations 2. Establish vibration limits based on building condition surveys: typically 5-10mm/s peak particle velocity for normal structures, 2-5mm/s for heritage buildings or structures with existing damage 3. Conduct trial breaking operations with vibration monitoring before full-scale pile removal, establishing actual vibration levels and safe working distances 4. Modify breaking techniques if vibration exceeds limits, including reduced breaker size, lighter impact energies, or alternative removal methods (cutting instead of breaking) 5. Restrict noisy breaking operations to approved hours typically 7am-6pm weekdays, avoiding early morning, evening, and weekend periods minimising community disruption 6. Implement operator rotation limiting individual operator exposure to maximum 2 hours continuous breaker operation followed by minimum 1 hour break performing non-vibration tasks 7. Provide anti-vibration gloves for equipment operators, though gloves provide limited protection and are supplement to exposure duration controls not replacement 8. Document all vibration monitoring results, maintaining records demonstrating compliance with protection criteria and available for regulatory authority review if complaints received

Structural Engineering Oversight and Load Path Verification

Administrative Control

Engage structural engineers to verify safe pile removal sequence and ensure load paths maintained throughout demolition preventing progressive collapse.

Implementation

1. Obtain structural engineering assessment before pile removal commencement, identifying load-bearing piles, load paths to remaining structures, and safe removal sequence 2. Implement sequential pile removal as specified by structural engineer, never removing multiple adjacent piles simultaneously if doing so could overload remaining piles 3. Install temporary support systems (propping, underpinning, ground improvement) where structural assessment identifies need before pile removal proceeds 4. Conduct structural inspections after each pile removal, checking adjacent structures for any movement, cracking, or distress indicating load transfer exceeding capacity 5. Engage structural engineer for site attendance during removal of critical piles supporting significant loads or in proximity to occupied structures 6. Document compliance with structural engineer's specifications including pile removal sequence, temporary works installation, and structural monitoring results 7. Establish stop-work authority allowing any worker to halt operations if structural distress observed, with no resumption until structural engineer confirms safety to proceed 8. Review and update demolition sequence if site conditions differ from anticipated, obtaining structural engineer approval before proceeding with modified sequence

Personal protective equipment

Respiratory Protection (P3 Respirator or Powered Air-Purifying Respirator)

Requirement: P3 particulate respirator providing minimum 99.95% filtration efficiency for silica dust; powered air-purifying respirator (PAPR) preferred for extended operations

When: Mandatory for all workers in dust-generating areas during concrete breaking operations, even when engineering controls (water suppression) implemented as backup protection

Full Face Shield and Safety Glasses

Requirement: Impact-rated full face shield worn over safety glasses providing comprehensive face and eye protection from flying debris

When: Required for equipment operators, workers within 5 metres of active breaking operations, and anyone entering exclusion zones during breaks in operations

Hearing Protection (Dual Protection)

Requirement: Earmuffs rated Class 5 (35dB reduction) worn over correctly fitted earplugs (Class 4, 25dB reduction) providing dual protection for extreme noise environments

When: Mandatory for breaker operators and all personnel within 20 metres of operating hydraulic breakers generating noise exceeding 110 dB(A)

Safety Helmet with Chin Strap

Requirement: Type 1 industrial safety helmet with four-point chin strap preventing dislodgement from overhead debris impact

When: Required for all personnel on demolition sites where overhead hazards from falling debris exist, including workers in excavations and observers

Steel Toe-Capped Safety Boots

Requirement: Safety footwear with steel toe caps, penetration-resistant midsole, and ankle support for uneven demolition site terrain

When: Mandatory for all site personnel where falling concrete segments or sharp reinforcement steel projections create foot injury hazards

High-Visibility Clothing

Requirement: Class D Day/Night high-visibility vest or jacket with minimum 0.2m² combined fluorescent and retroreflective material

When: Required for all ground personnel ensuring visibility to equipment operators during lifting and demolition operations

Cut-Resistant Gloves

Requirement: Level 5 cut-resistant gloves providing protection when handling concrete segments with exposed sharp reinforcement steel

When: Required during manual handling of broken pile segments and when working near exposed reinforcement bars

Inspections & checks

Before work starts

  • Verify structural engineering approval obtained and pile removal sequence documented and understood by all personnel
  • Confirm geotechnical report reviewed identifying ground conditions, required shoring specifications, and any special precautions for unstable soils
  • Inspect demolition equipment including hydraulic breakers, crushers, excavators verifying capacity ratings, hydraulic system integrity, operator cab protection, and current maintenance certifications
  • Check water suppression systems confirming adequate water supply, functioning pumps, spray nozzles clear and properly positioned, and automatic activation systems operational
  • Verify atmospheric testing equipment calibrated within previous 30 days and functioning correctly (conducting bump test with calibration gas)
  • Inspect excavation shoring materials (if applicable) confirming adequate quantity for anticipated excavation depths and compliant with geotechnical specifications
  • Confirm ground movement monitoring installed on adjacent structures with baseline readings recorded before pile removal commencement
  • Verify exclusion zone barriers erected and signage installed preventing unauthorised entry to debris projection areas
  • Check that all workers completed site-specific induction covering pile removal hazards, emergency procedures, and communication protocols
  • Inspect weather forecast ensuring no heavy rain forecast that could saturate soils increasing excavation collapse risks or strong winds that could spread dust beyond site boundaries

During work

  • Monitor dust generation continuously, verifying water suppression operating effectively with no visible dust clouds escaping work area
  • Observe ground conditions around excavations hourly checking for any signs of instability including wall bulging, tension cracks at surface, or water seepage undermining excavation walls
  • Verify exclusion zones maintained with no unauthorised personnel within debris projection areas during active breaking operations
  • Conduct atmospheric testing at minimum 2-hour intervals when workers occupied in excavations exceeding 1.5 metres depth, more frequently if any gas detection occurs
  • Check ground movement monitoring readings before commencing work each shift and after each pile removal, comparing to trigger levels and immediately stopping work if limits exceeded
  • Monitor vibration levels on adjacent structures verifying peak particle velocity remains below established limits, reducing breaker intensity or modifying techniques if limits approached
  • Observe equipment operator fatigue levels particularly during extended breaking operations, implementing additional breaks if concentration deterioration observed
  • Verify debris containment barriers remain intact and positioned correctly, repairing or adjusting if damage or displacement observed
  • Check that workers maintaining correct PPE use including respiratory protection, face shields, and hearing protection throughout dust and noise exposure periods
  • Monitor pile void backfilling progress ensuring voids filled promptly after segment removal preventing void migration or delayed collapse

After work

  • Inspect completed excavation areas verifying all pile segments removed, voids completely backfilled, and compaction testing completed confirming specified density achieved
  • Conduct final ground movement survey on adjacent structures comparing to baseline readings and documenting any settlement or movement that occurred during pile removal
  • Verify all excavations either backfilled or adequately protected with barriers preventing public access if works extending over multiple shifts
  • Check demolition equipment cleaned including removal of concrete dust from hydraulic systems, operator cabins, and control mechanisms preventing premature wear
  • Document pile removal progress including number of piles removed, cubic metres of concrete disposed, and any variations from planned removal sequence
  • Complete atmospheric monitoring records if confined space entry occurred, maintaining documentation for regulatory compliance and health surveillance programs
  • Inspect adjacent structures for any visible damage (new cracks, displaced elements, settlement indicators) requiring remedial action or further structural engineering assessment
  • Debrief crew regarding safety observations, near-misses, or technique improvements identified during shift for incorporation into subsequent operations
  • Verify all waste materials segregated appropriately with concrete debris stockpiled for crushing or disposal, reinforcement steel segregated for recycling, and any contaminated materials (asbestos, lead paint) isolated for specialist disposal
  • Secure site ensuring all equipment isolated from unauthorised use, excavations protected, and emergency contact information posted for after-hours incidents

Step-by-step work procedure

Give supervisors and crews a clear, auditable sequence for the task.

Field ready
1

Pre-Demolition Survey, Structural Assessment, and Hazardous Materials Identification

Engage structural engineer to conduct comprehensive assessment of existing structure identifying pile locations from as-built drawings, physically exposing representative piles to verify actual construction versus documented details, assessing structural load paths determining which piles are load-bearing and must be removed in specific sequence to prevent progressive collapse, and specifying temporary support requirements if needed. Commission asbestos and hazardous materials survey to identify any asbestos-containing materials in pile wrapping or coatings (particularly relevant for piles constructed before 1990 when asbestos use was common), lead-based paints, or soil contamination around pile sites. Obtain geotechnical investigation report characterising soil conditions, groundwater levels, bearing capacity, and any known instabilities affecting excavation safety. Review dial-before-you-dig responses and engage locators to identify underground services that may be damaged during excavation or pile removal operations. **Safety Considerations:** Structural assessment is critical preventing unintended collapse from removing piles supporting significant loads without understanding load transfer to remaining elements. Asbestos in pile construction materials requires specialist removal before mechanical breaking commences as breaking asbestos-containing materials creates severe health hazards. Test excavations to physically inspect piles require same excavation safety controls as main works including shoring if exceeding 1.5 metres depth. Desktop review of historical site uses may identify soil contamination requiring environmental assessment and specialist handling. **Related Hazards:** Structural collapse if load paths not understood before pile removal, asbestos exposure if ACM present and not identified, excavation collapse during test excavations, underground service strikes during investigation works.

2

Site Establishment, Ground Monitoring Installation, and Control Implementation

Establish site controls including perimeter fencing restricting public access, signage identifying hazards and emergency contacts, amenities for workers including clean drinking water and washing facilities for dust removal, and designated material storage areas segregating concrete waste from recyclable steel reinforcement. Install ground movement monitoring systems on adjacent structures including optical survey targets at multiple elevations allowing three-dimensional movement detection, crack width gauges on existing structural cracks to detect widening, and inclinometers in deep excavations detecting lateral wall movement. Conduct baseline monitoring surveys before pile removal commences establishing reference conditions for comparison during operations. Set up water suppression infrastructure including water storage tanks (minimum 10,000-litre capacity), high-pressure pumps (minimum 400 kPa delivery pressure), distribution pipework to work areas, and misting nozzle arrays around anticipated breaking locations. Position atmospheric monitoring equipment and test all gas detection functions. **Safety Considerations:** Ground monitoring is essential providing early warning of excessive movement before catastrophic failure occurs, but monitoring is useless without established trigger levels and stop-work procedures if limits exceeded. Water suppression infrastructure must be operational before any concrete breaking commences as retrospective dust control is ineffective. Atmospheric testing equipment requires calibration verification before relying on readings for confined space entry decisions. Site establishment creates manual handling exposures from moving equipment and materials requiring mechanical assistance where items exceed safe manual handling limits. **Related Hazards:** Ground movement undetected if monitoring inadequate, silica exposure if water suppression not ready before breaking commences, atmospheric hazards in excavations if testing equipment uncalibrated, manual handling injuries during site establishment.

3

Excavation Around Pile Heads and Shoring Installation

Excavate carefully around pile heads using mini-excavator or hand tools exposing sufficient pile length for demolition equipment access while maintaining soil stability around excavation perimeter. Typical excavation depth is 1.5-2.5 metres depending on pile diameter and breaking equipment requirements. Locate excavation to provide stable working platform for demolition equipment positioned adjacent to pile. Install excavation shoring progressively as excavation deepens, never excavating ahead of shoring protection where depths exceed 1.5 metres or soils are unstable. Shoring systems may include hydraulic struts with waler beams, trench shields positioned around excavation perimeter, or benching excavation walls at stable angles (typically 1:1 or flatter for cohesionless soils). Verify groundwater not accumulating in excavation bottom creating instability; implement dewatering if seepage observed. Establish safe access and egress using securely positioned ladders at maximum 8-metre intervals for excavations exceeding 2 metres depth. Install edge protection barriers minimum 1 metre from excavation edge preventing vehicles or mobile plant approaching too close. **Safety Considerations:** Excavation collapse is the most immediate life-threatening hazard during pile exposure phase, with collapse occurring suddenly and burial typically fatal if depth exceeds 1.5 metres. Never enter excavations exceeding 1.5 metres depth without shoring installed regardless of apparent soil stability. Groundwater seepage can rapidly undermine excavation walls even in soils that appear initially stable. Excavation around existing piles can expose unexpected buried obstructions including abandoned services, old foundations, or buried waste creating additional hazards requiring assessment before proceeding. Confined space hazards can develop in deep excavations requiring atmospheric testing before worker entry. **Related Hazards:** Excavation collapse and burial, groundwater-related instability, confined space atmospheric hazards, service strikes when excavating around piles, manual handling when installing shoring systems.

4

Dust Suppression Activation and Breaking Equipment Setup

Position water suppression system around pile to be demolished, directing misting nozzles to create water curtain encompassing pile and breaking equipment operating zone. Activate water flow and verify coverage adequate with fine mist visible around entire work area. Position excavator with hydraulic breaker attachment on stable ground with secure footing preventing equipment tipping or sinking during breaking operations. Verify excavator capacity adequate for breaker size (typically breaker weight should not exceed 10-15% of excavator operating weight to prevent instability). Fit appropriate breaker tool for pile breaking—typically chisel point or moil point for initial fracture, blunt tool for progressive breaking. Test breaker operation before commencing pile breaking, checking hydraulic pressure, oil flow, and impact frequency. Establish exclusion zone minimum 15 metres radius around active breaking operations, marked with barriers and signs. Position observer outside exclusion zone maintaining communication with breaker operator via two-way radio, responsible for ensuring zone remains clear and monitoring for flying debris, ground movement, or other developing hazards. **Safety Considerations:** Water suppression must be operating continuously during all breaking operations without interruption as even brief dry breaking generates hazardous dust concentrations. Excavator stability is critical as breaker reaction forces can destabilise equipment particularly when operating on sloped ground or soft excavation spoil. Undersized excavators for breaker weight will experience excessive movement and potential tip-over when breaking resistant concrete. Breaker tool selection affects breaking efficiency and debris projection characteristics—sharp tools create more violent fracture with greater debris projection versus blunt tools causing crushing action. Exclusion zone dimensions depend on pile size and breaker power with larger piles requiring larger zones. **Related Hazards:** Silica dust exposure if water suppression fails, flying debris from pile fracture, excavator instability or tip-over, hydraulic system failures, noise exposure exceeding 110 dB(A).

5

Progressive Pile Breaking and Segmentation

Commence pile breaking at pile head working progressively downward in manageable segments. Begin with low breaker impact force assessing concrete resistance and adjusting breaker power to achieve efficient breaking without excessive violent fracture increasing debris projection. Break pile into segments approximately 500mm-1 metre length allowing mechanical lifting and removal without exceeding excavator or crane capacity. Create circumferential break lines around pile perimeter before attempting to separate segments as trying to fracture long sections creates instability and loss of control. Watch for reinforcement steel becoming exposed; when steel bars visible, use cutting torch or hydraulic shears to sever reinforcement before further breaking as attempting to break through dense steel is inefficient and creates excessive vibration. Monitor water suppression system continuously ensuring adequate coverage as breaking progresses; increase water flow if any dust generation observed. Conduct periodic atmospheric testing if working in confined excavation particularly if odours detected or workers report breathing difficulty. Stop breaking operations immediately if ground movement detected, structural engineer consultation required before resuming. **Safety Considerations:** Progressive breaking from top down is safest sequence preventing unsupported concrete sections above becoming unstable and falling onto workers or equipment. Breaking creates intense vibration transmitted through pile into ground and adjacent structures; monitor vibration levels and reduce breaker power or modify technique if limits approached. Exposed reinforcement bars are extremely sharp creating laceration hazards when handling broken segments. Cutting reinforcement using oxy-acetylene cutting creates hot work hazards including fire risk from sparks, burns from hot metal, and fume exposure requiring ventilation. Never break from pile bottom upward as this creates unstable conditions with concrete above potentially collapsing unexpectedly. **Related Hazards:** Flying debris during breaking, silica dust if suppression inadequate, ground vibration affecting adjacent structures, lacerations from exposed reinforcement, hot work hazards when cutting steel, ground movement if pile removal sequence incorrect.

6

Broken Segment Removal and Void Management

Remove broken pile segments from excavation using excavator bucket or crane with chain slings, lifting segments clear of excavation and placing in designated concrete waste stockpile area. Inspect each segment before lifting checking for unstable concrete that could separate during lifting and become falling objects. Use chain slings rather than bucket grab where segments have irregular shapes preventing secure gripping. Maintain exclusion zone under suspended loads preventing personnel beneath during lifting operations. Segregate reinforcement steel from concrete for recycling, cutting steel into manageable lengths using hydraulic shears or cutting torch. As pile segments are removed exposing pile void in ground, immediately backfill void using controlled fill material (typically crusher dust, sand-cement mix, or flowable fill) preventing void migration downward or laterally that could undermine adjacent piles or structures. Compact backfill material in maximum 300mm lifts using hand-operated compactors or excavator bucket tamping for confined excavations. Verify adequate compaction through physical inspection and test rolling where accessible. **Safety Considerations:** Lifting irregular concrete segments is high-risk operation as unexpected load shift during lifting can cause load to fall or crane to overturn. Always lift vertically without dragging loads across excavation edge potentially dislodging unstable soil. Suspended load exclusion zones must be rigidly enforced as falling concrete causes fatal crushing injuries. Steel reinforcement cutting creates same hot work hazards as earlier cutting operations plus potential for cut steel under tension springing back striking operator. Backfilling pile voids promptly prevents delayed ground collapse that could occur hours or days after pile removal when workers no longer anticipating hazard. Inadequately compacted backfill creates future settlement problems potentially causing surface structure damage. **Related Hazards:** Struck-by hazards from falling suspended loads, crane instability when lifting irregular loads, lacerations from steel reinforcement, hot work hazards during steel cutting, ground collapse if voids not promptly backfilled, traffic hazards if waste stockpiles obstruct vehicle movements.

7

Ground Monitoring Review and Adjacent Structure Inspection

Conduct ground movement monitoring surveys after each pile removal comparing current readings to baseline conditions and identifying any settlement or lateral movement of adjacent structures. Calculate cumulative movement from commencement of works determining whether total movement approaching trigger levels requiring work modification or cessation. Physically inspect adjacent structures looking for new cracks in masonry, distortion of door or window frames indicating structural movement, or separation between building elements suggesting differential settlement. Photograph any observed damage documenting condition before and after pile removal operations for objective comparison. If movement detected exceeding first trigger level (typically 5mm), notify structural engineer and implement enhanced monitoring frequency increasing to minimum twice-daily surveys. If movement exceeds stop-work trigger level (typically 10mm), immediately cease all pile removal operations and engage structural engineer for emergency assessment before any resumption. Document all monitoring results in project records demonstrating compliance with structural protection criteria. **Safety Considerations:** Ground movement monitoring is protective measure only if results are reviewed and acted upon when limits exceeded. Monitoring without defined trigger levels and response procedures is meaningless. Movement detection requires comparison to baseline conditions making accurate baseline surveys before work commencement essential. Some ground movement is inevitable during pile removal; the question is whether movement remains within acceptable limits or exceeds structural capacity of adjacent buildings. Delayed settlement can occur hours or days after pile removal as ground consolidates making post-work monitoring as important as during-work monitoring. Vibration from breaking operations can trigger cracking in already stressed structures appearing unrelated to settlement but requiring same assessment. **Related Hazards:** Structural damage to adjacent buildings from excessive settlement, delayed ground collapse occurring after work completion, third-party liability claims for property damage, progressive deterioration of structures with initial minor damage worsening over time.

Frequently asked questions

What are the legal requirements for silica dust control during concrete pile breaking in Australia?

Silica dust control during concrete pile breaking must comply with workplace exposure standards and WHS regulations implementing hierarchy of control. The current workplace exposure standard for respirable crystalline silica is 0.05 mg/m³ eight-hour time-weighted average, reduced from previous 0.1 mg/m³ standard implemented in most jurisdictions from December 2020. This exposure standard is legally enforceable with significant penalties for non-compliance. PCBUs must implement controls following hierarchy: elimination where possible (avoiding breaking through alternative methods like cutting or chemical expansion), engineering controls as primary approach (water suppression, on-tool extraction, enclosure), administrative controls supplementing engineering (job rotation, air monitoring, work scheduling), and PPE as final protection layer (respiratory protection rated minimum P2 though P3 recommended for high-exposure tasks). Water suppression represents the most effective practical engineering control for pile breaking, capable of reducing airborne dust by 90-95% when properly implemented. Requirements extend beyond exposure control to include air monitoring using personal sampling pumps to quantify actual worker exposures and verify control effectiveness, health surveillance programs including baseline and periodic medical examinations with respiratory function testing and chest X-rays for all workers with silica exposure, record keeping maintaining exposure monitoring and health surveillance records for minimum 30 years, and provision of information and training to all workers covering silica health effects, exposure scenarios in their work, and correct use of control measures. Specific regulatory requirements exist for licenced asbestos assessors to attend sites built before 1990 as asbestos was commonly used in pile construction, with asbestos removal requiring Class B asbestos removal licence if more than 10 square metres ACM present. WorkSafe authorities across Australian states actively enforce silica regulations through workplace inspections, with common compliance issues including inadequate or non-functioning water suppression systems, workers not wearing respiratory protection or wearing wrong respirator type, lack of air monitoring to verify exposure levels, and absence of health surveillance programs. Penalties for serious breaches can exceed $500,000 for organisations, with individual officers also liable where breaches result from their negligence or failure to exercise due diligence. Following serious silica exposure incidents, WorkSafe may issue prohibition notices immediately stopping all work until adequate controls implemented, and may prosecute PCBUs and officers with potential criminal conviction and jail terms in extreme cases.

How do you determine safe pile removal sequence to prevent structural collapse?

Safe pile removal sequence must be determined by qualified structural engineer through comprehensive assessment before any physical pile removal commences. The engineering assessment process includes: structural load path analysis identifying which piles carry significant structural loads from remaining buildings or structures versus decorative or non-structural piles that can be removed in any sequence; soil-structure interaction modelling evaluating how pile removal affects load distribution to adjacent piles and whether remaining piles have adequate capacity to carry redistributed loads; temporary works design specifying any propping, underpinning, or ground improvement required before pile removal to maintain structural stability; and establishment of removal sequence documentation prescribing exact order for pile removal with any restrictions on concurrent pile removals (e.g., never remove two adjacent load-bearing piles simultaneously). The structural assessment must consider: dead loads from building weight, live loads from occupancy and stored materials, dynamic loads from equipment or traffic, wind loads on remaining structure, and construction loads from demolition equipment and stockpiled materials. For load-bearing piles supporting active structures, generally required to remove piles working from perimeter toward centre, removing non-critical piles first before addressing heavily loaded elements, never creating situations where remaining piles loaded beyond design capacity even temporarily, and implementing contingency measures including real-time structural monitoring detecting excessive deflection or stress. Pile removal sequence becomes critical where: buildings remain occupied during pile removal requiring absolute certainty no collapse risk exists; multiple structures share interconnected pile foundation systems where removing piles for one building affects adjacent buildings; heritage structures with brittle unreinforced masonry extremely sensitive to settlement or movement; or contaminated sites where pile removal could trigger ground subsidence allowing contaminated material migration. The structural engineer should specify: individual pile identification clearly matching site conditions, maximum number of piles permitted to be removed per day or shift limiting cumulative impact, mandatory hold points requiring engineer inspection before proceeding to next phase, monitoring requirements including survey monitoring frequency and trigger levels, and emergency procedures if unexpected structural behaviour observed. All site personnel must understand and follow structural engineer's sequence specifications exactly without deviation, as unauthorised sequence changes could trigger collapse. If conditions differ from anticipated (piles in different locations, different sizes, unexpected structural elements discovered), work must stop pending engineer reassessment rather than proceeding with modified sequence based on site judgement. Document compliance meticulously including photographs before and after each pile removal, monitoring results, and engineer sign-offs at hold points, as this documentation provides evidence of proper procedures if structural issues emerge later.

What atmospheric hazards can develop in deep pile excavations and how should they be controlled?

Deep excavations around pile bases can develop multiple atmospheric hazards requiring confined space management protocols. Oxygen deficiency (atmosphere containing less than 19.5% oxygen) can result from: bacterial decomposition of organic matter in soil consuming oxygen and producing carbon dioxide; displacement of oxygen by heavier gases (CO₂) that layer in excavation bottom; rust oxidation consuming oxygen if buried steel present; or any combustion or chemical reaction depleting oxygen. Toxic gases include hydrogen sulfide from decaying organic matter or sewage, carbon monoxide from equipment exhaust or fires, sewer gases (methane, ammonia, hydrogen sulfide mixture) if excavation intercepts sewer lines or septic systems, and volatile organic compounds from soil contamination with petroleum products or industrial chemicals. Combustible gases including methane from decomposing organic matter, petroleum vapours from contaminated soil, or natural gas from leaking underground pipelines can accumulate creating explosion hazards if ignition source introduced. Control measures following hierarchy include: elimination through avoiding deep excavations where possible, designing pile removal to minimise excavation depth, or using remote-controlled demolition equipment operating from surface eliminating worker entry; engineering controls including continuous forced mechanical ventilation delivering minimum 6 air changes per hour using portable blowers with ducting directing airflow to excavation bottom (where hazard concentrations highest), exhaust fans extracting contaminated air from excavation, or natural ventilation through excavation geometry if excavation wide relative to depth allowing air circulation; administrative controls including atmospheric testing before every entry and continuously during occupation using calibrated four-gas monitors measuring oxygen percentage (must be 19.5-23.5%), combustible gas (must be below 10% lower explosive limit), carbon monoxide (must be below 30 ppm), and hydrogen sulfide (must be below 10 ppm), confined space entry permits authorising entry only after acceptable atmospheric testing, designation of standby person outside excavation maintaining communication with workers below and capable of summoning rescue without entering, and prohibition on entry if atmospheric hazards detected regardless of schedule pressures; and PPE including supplied-air respirators or self-contained breathing apparatus (SCBA) if entry required despite atmospheric hazards for emergency purposes only, never as routine control permitting entry into hazardous atmospheres for normal work. Critical errors to avoid include: assuming excavations safe to enter without testing because they 'look fine' (toxic gases and oxygen deficiency are invisible and odourless), relying on past testing without current verification (atmospheric conditions can change rapidly particularly if organic decomposition occurring), using inappropriate testing equipment (combustible gas detectors measure different gases than toxic gas monitors), entering excavations to rescue overcome workers without breathing apparatus (creating secondary casualties), and treating shallow excavations casually without testing (atmospheric hazards can develop in excavations less than 2 metres deep). Always classify excavations exceeding 1.5 metres depth as potential confined spaces requiring full testing protocols, maintain testing equipment calibration within 30 days, and provide comprehensive training to all workers covering atmospheric hazard recognition, correct testing procedures, emergency response without entry, and strict prohibition on unauthorised entry bypassing testing requirements.

What vibration limits apply to protect adjacent structures during pile breaking operations?

Vibration limits for protecting adjacent structures during pile breaking must be established based on building condition surveys conducted by structural engineers before work commencement. Standard criteria exist but must be adapted to actual building conditions: British Standard BS 7385 'Evaluation and Measurement for Vibration in Buildings' provides widely-accepted guidance suggesting peak particle velocity (PPV) limits of 15-20 mm/s for transient vibration in reinforced concrete or framed structures, 15 mm/s for unreinforced or light-framed residential structures, and 3-5 mm/s for heritage buildings or structures with existing damage. Australian Standard AS 2187.2 'Explosives - Storage and Use: Use of Explosives' provides similar criteria originally developed for blasting but applicable to impact sources including pile breaking. However, these are guidelines requiring engineering assessment for specific applications. The structural engineer's building condition survey identifies: existing structural damage including cracks, spalling, or previous repairs indicating reduced vibration tolerance; structural type and construction materials with brittle materials (unreinforced masonry, terracotta, plaster) more sensitive than ductile materials (steel, reinforced concrete); building age with older structures generally more sensitive due to deteriorated mortar, corroded reinforcement, or non-compliant original design; building use with occupied structures, hospitals, laboratories with sensitive equipment, or heritage buildings requiring more conservative limits; and soil conditions with buildings on soft or saturated soils experiencing amplified vibration compared to rock or dense soil foundations. Based on survey findings, engineer specifies project-specific limits typically ranging: 2 mm/s PPV for extremely sensitive heritage buildings with significant existing damage, 5 mm/s PPV for normal heritage buildings or sensitive structures, 10 mm/s PPV for sound residential buildings, 20 mm/s PPV for commercial or industrial structures with no existing damage, and 50 mm/s PPV for robust construction with no sensitivity (though this level rarely permitted for occupied buildings). Implement vibration monitoring using: triaxial seismographs mounted directly on structures being protected recording vibration in three dimensions, real-time monitoring with alarm thresholds alerting when limits approached allowing immediate work modification, continuous logging throughout breaking operations maintaining permanent records, and baseline surveys before work documenting existing vibration from traffic or other sources for comparison. If vibration exceeds 80% of limit values, implement immediate corrective actions including reducing breaker impact energy, using smaller breaker, switching to alternative removal method (cutting instead of breaking), increasing standoff distance between breaking location and sensitive structure, or implementing vibration isolation (rubber mats, sand blankets) though effectiveness of isolation is limited for ground-borne vibration. If limits exceeded despite modifications, cease work immediately and reassess methodology potentially switching to vibration-free methods like chemical expansion breaking or diamond wire cutting. Document all vibration monitoring results with timestamps, locations, and concurrent activities, maintaining records demonstrating compliance if complaints received or damage claims made. Conduct post-work structural inspections photographically documenting building condition allowing objective comparison to pre-work condition if disputes arise about damage causation.

Related SWMS documents

Browse all documents
Trusted by 1,500+ Australian construction teams

Concrete Pile Removal SWMS Sample

Professional SWMS created in 5 seconds with OneClickSWMS

  • Instant PDF & shareable link
  • Auto-filled risk matrix
  • Editable Word download
  • State-specific compliance
  • Digital signature ready
  • Version history preserved
Manual creation2-3 hours
OneClickSWMS5 seconds
Save 99% of admin time and eliminate manual errors.

No credit card required • Instant access • Unlimited drafts included in every plan

PDF Sample

Risk Rating

BeforeHigh
After ControlsLow

Key Controls

  • • Pre-start briefing covering hazards
  • • PPE: hard hats, eye protection, gloves
  • • Emergency plan communicated to crew

Signature Ready

Capture digital signatures onsite and store revisions with automatic timestamps.